Configuration Baselines

A known-good record of how every part of the control system is configured, captured at acceptance and kept current through change management: what to baseline, how to capture and store it, how to compare on a schedule, and what an unexplained difference means.

8 min readUpdated Sep 5, 2026Published Sep 5, 2026By Eric Sullivan

The short answer

Configuration Baselines

A configuration baseline is the documented, stored, known-good configuration of each asset: the controller program and its checksum or signature, the SCADA project and its version, the server build against its hardening baseline, the firewall and switch configurations, and the firmware version and parameter set of each device. It is captured at acceptance after the system has been tested, stored under version control with the date and the person, updated only through change management when a change is approved, and compared against the live system on a schedule. A difference that matches an approved change updates the baseline; a difference that matches nothing is an unauthorized change and is treated as a potential incident until it is explained.

Key points

  • The baseline is what the system is supposed to look like; without it, a change cannot be recognized as one.
  • Capture at acceptance, after testing, and store under version control with date and author.
  • The baseline changes only through change management; the update is the last step of every approved change.
  • Compare live against baseline on a schedule, automated where the platform allows.
  • An unexplained difference is an incident until explained, not a curiosity.
  • Controller signatures, project versions, device configurations, firmware versions: each has a way to be compared.

What to baseline

AssetWhat is capturedHow it is compared
Controllers and remote unitsThe project file, the program checksum or signature the controller reports, the firmware version, the configuration of modules and communicationsVendor compare tools, or the checksum read by the SCADA and compared with the stored value
HMI panelsThe project file and its version, the runtime versionProject compare or version check
SCADA serversThe project export, the tag and alarm database, scripts, the application versionVendor version control or a file-level compare of the export
Servers and workstationsThe build against the hardening baseline: services, features, firewall rules, accounts, installed software, policiesA configuration audit script or a compliance tool that reports differences
Network devicesFirewall rules, switch configurations, VLANs, port settings, radio configurationsText compare of the configuration export against the stored one
Instruments and drivesFirmware version and the parameter set: ranges, scaling, protection settings, communication addressesParameter export compared with the stored export; firmware version read from the device
DocumentationFunctional description, drawings, IP schedule, the baseline records themselvesRevision numbers

Capturing it

  1. 1

    Wait for acceptance

    The baseline is the tested, accepted configuration, not the one from the day the equipment arrived. Capture it after commissioning is signed off.

  2. 2

    Collect

    Every item in the table, from the actual live system: upload from the controllers, export from the servers and devices, read the firmware versions from the equipment.

  3. 3

    Store

    In a version control system or a controlled repository, with the date, the person, and a note that this is the acceptance baseline. The repository is backed up and included in the offline copy.

  4. 4

    Record the signatures

    Where a controller or a device provides a checksum or a signature of its configuration, record it beside the file; the signature is what can be checked without uploading the whole program.

  5. 5

    Make it the reference

    The change management process points at the repository; every change record names the baseline version it started from and the one it produced.

Comparing

The comparison is a scheduled task: monthly for most assets, weekly or continuous for the controllers that matter most. Where the platform provides tools, the comparison is automatic: a version control product uploads each controller on a schedule and compares it with the stored project, and reports differences with who and when; a compliance tool audits the server build; the SCADA reads the controller change counter or signature and alarms when it moves. Where it does not, a person exports the configuration and compares it with the stored one, which is tedious and still worth doing for firewalls, switches, and critical controllers. The output is a list of differences, each of which is one of three things.

DifferenceMeaningAction
Matches an approved change recordThe change was made as approved and the baseline was not yet updated, or the schedule caught it firstUpdate the baseline; close the change record
Matches an emergency change that was documented afterwardSomeone fixed something under pressure and recorded it laterUpdate the baseline; review whether the emergency process worked
Matches nothingAn unauthorized change: a well-meaning edit, a vendor session nobody recorded, a mistake, or an intrusionTreat as an incident: find who, when, and what, from logs and interviews; assess the change; revert or approve; and fix the gap that allowed it

Keeping it alive

Baselines die when the update step is skipped: a change is made, the record is closed, and the repository still holds the old version. Within a year every comparison shows differences, the differences are all explained by memory, and the practice is abandoned. The defense is to make the baseline update the last mandatory step of the change record, checked by whoever closes it, and to run the comparison on a schedule so that a missed update is caught in a month rather than a year.

Frequently asked questions

Is the integrator project archive a baseline?
It is a starting point, and it is often not what is running: changes during commissioning and afterward were made online and never returned to the archive. Upload from the live system at acceptance, compare with the archive, resolve the differences, and store the result as the baseline.
How much do version control tools for controllers cost?
Vendor and third-party products that upload, compare, and record controller programs on a schedule are priced for plants of some size and pay for themselves at the first unexplained change. A small utility can do the same by hand for a handful of controllers with the vendor compare function and a repository, on a monthly calendar entry.
What about setpoints operators change every day?
Operating setpoints within their limits are operations, not configuration, and they are not in the baseline; the limits are. A setpoint changed outside its limits, or a limit changed, is a configuration change and goes through change management.
Do we baseline the office computers that never touch the plant?
No; the baseline covers the control system and what protects it. The engineering workstation that programs controllers is in; the manager laptop with a view-only web client is the office IT department concern, with the firewall between them.