SCADA Backups

What a SCADA backup must contain to bring a system back: the project export, an image of each server, the databases, historian archives, licenses, certificates, scripts, and network device configurations, with frequency, retention, and the restore procedure.

9 min readUpdated Sep 5, 2026Published Sep 5, 2026By Eric Sullivan

The short answer

SCADA Backups

A SCADA backup is several backups: an export of the application project in the vendor format after every change, an image of each server on a schedule and before every patch, the databases that hold the alarm journal and configuration daily, the historian archive files as they close, the license files and activation records, certificates and keys, scripts, report templates, and custom code, and the configuration files of the firewalls, switches, and radios that the system depends on. Each has its own frequency and retention, multiple versions are kept so that a backup taken after a compromise does not overwrite the last clean one, copies are kept in three places including one offline, the backups are encrypted and their completion is monitored, and a restore procedure is written and tested so that the backups can actually be used.

Key points

  • The project export and the server image are different backups with different uses; keep both.
  • Licenses, activation records, certificates, and installers are part of the backup, or the restore stops at the license prompt.
  • Historian archives are regulatory records; they are backed up as files as they close.
  • Keep versions, not just the latest; the latest may already be compromised.
  • Three copies, two kinds of media, one offline; monitored, encrypted, and documented.
  • A backup without a tested restore procedure is a file with hope in it.

What has to be in it

ItemMethodFrequencyRetention
Application projectExport in the vendor project format, with displays, tags, alarms, scripts, and security configurationAfter every change, and weeklyEvery version for a year; milestones forever
Server imagesFull image of each virtual machine or physical serverWeekly, and before every patch or upgradeSeveral weeks of versions; one per quarter for a year
DatabasesDatabase backup of the alarm journal, audit trail, configuration, and reporting databasesDaily, with transaction logs where the database supports themThirty days online; monthly for the record period
Historian archivesFile backup of archive files as they close, plus the active archive dailyDailyThe retention policy for the data, which may be years
Licenses and activationLicense files, activation codes, vendor account details, dongle recordsOn every changeForever, with the images
Certificates and keysServer certificates, private keys, OPC UA certificates, VPN keys, with their passwords in the vaultOn every changeUntil expiry plus one year
Scripts, reports, custom codeFile backup of everything not in the project exportAfter every changeEvery version
Network device configurationsFirewall, switch, router, and radio configuration exportsAfter every change, and monthlyEvery version
Installers and mediaThe installation packages for the SCADA version in use, the operating system, and third-party softwareWhen a version is installedUntil the version is retired
DocumentationThe functional description, drawings, IP schedule, restore procedure, and the vault exportOn every changeEvery version

Two kinds of backup

A project export is what the vendor software can import: it restores the application onto a freshly installed server, survives a version change, and can be inspected and compared. A server image is what the hypervisor or the imaging tool can restore: it brings the whole machine back in minutes, exactly as it was, on the same or compatible hardware. The image is the fast path after a hardware failure or a bad patch; the project export is the path after a compromise, when the image cannot be trusted, and after a platform upgrade, when the image is the wrong version. A system with only images cannot be rebuilt clean; a system with only project exports takes a day to rebuild. Keep both.

Versions and places

Ransomware often sits in a system for weeks before it acts, and a backup taken during that time contains it. Keeping only the latest backup means the last clean copy has been overwritten by the time anyone notices. Retention keeps versions going back months, with milestones kept indefinitely. The three-two-one rule places three copies on two kinds of media with one off site, and the control system version adds one offline: a copy that no network, no credential, and no process on the control network can reach, which is the copy that survives the day everything else is encrypted.

Mechanics

  • Backups are automated and scheduled; a backup that depends on someone remembering is taken until they forget.
  • Completion and size are monitored and alarmed; a job that fails silently for a month is a month with no backup.
  • Backup data is encrypted, and the key is in the vault and in the break-glass envelope, not on the backup server.
  • The backup target is on the control network or the DMZ with a one-way push, not on the office file server.
  • Backup credentials are unique to the backup service and are not the domain administrator.
  • A restore procedure is written for each item, tested, and kept where it can be read with the servers down.

The restore procedure

For each item, the procedure says where the backup is, what it is restored onto, in what order, with what credentials and licenses, and how the result is verified. For a server it includes the license reactivation with the vendor contact, the archive re-registration for the historian, the reconnection of clients, and the alarm state check. For the project export it includes the fresh installation of the platform at the right version. The procedure is exercised at least once a year, timed, and corrected, and the time it takes is the recovery time the utility should plan around.

Frequently asked questions

How often should the project be exported?
After every change, as part of the change record, and on a weekly schedule to catch what was missed. Exports are small and versions are cheap; a change that was made and not exported is a change that has to be made again after a restore.
Do virtual machine snapshots count as backups?
No. A snapshot lives on the same storage as the machine, grows until it hurts performance, and is lost with the storage. Snapshots are for rolling back a patch within hours; backups are copies elsewhere. Take a backup before the patch as well as the snapshot, and delete the snapshot afterward.
What about the operator consoles?
An image of the standard client build, kept current, plus the project deployment. Individual consoles are not backed up; they are reimaged from the standard build, which is faster and cleaner than restoring a machine that has accumulated years of drift.
Who is responsible?
A named person, with a schedule, a monitoring alarm that reaches them, and an annual test that management sees the result of. Backups at most utilities fail through neglect rather than technology, and the fix is a name.