Headworks Control

The first stop for raw wastewater: influent flow measurement, mechanical screens and their differential level control, grit removal, influent pumping where the plant needs it, the odor and hazardous atmosphere considerations that shape the electrical design, and what SCADA needs from the headworks.

10 min readUpdated Sep 5, 2026Published Sep 5, 2026By Eric Sullivan

The short answer

Headworks Control

The headworks receives raw wastewater, measures it, removes the material that would damage downstream equipment, and delivers it to treatment. Its controls run the screens on a differential level across the screen with a timed backup, run the grit removal on flow or on a schedule, pace the screenings and grit handling to the screens, and measure the influent flow that every downstream process and the permit depend on. The headworks is a wet, corrosive, and often classified hazardous location, and the instruments and panels are specified for it.

Key points

  • The influent flow meter is a compliance measurement and the pacing signal for the plant. It gets the best installation on site.
  • Screens clean on differential level across the screen, with a timer as backup and a high differential alarm.
  • Grit removal runs on flow or on a schedule; the grit pump and classifier are paced to it.
  • Much of the headworks is a Class I, Division 1 or 2 location. Instruments, panels, and wiring are rated for it.
  • The headworks is where a storm arrives first. Rate-of-rise alarms and bypass logic live here.

What the headworks does

Everything the collection system delivers arrives at the headworks: wastewater, rags, grit, wipes, sticks, the occasional bicycle. The headworks measures the flow, screens out the large material, settles out the grit, and passes the water on to primary or secondary treatment. Its equipment runs in the harshest environment on the plant, with hydrogen sulfide, moisture, and abrasive solids, and its failure sends the debris downstream into pumps, diffusers, and clarifier mechanisms. The controls are simple in concept and unforgiving in detail.

Influent flow

The influent flow measurement is the number the plant runs on. It paces chemical feeds, it drives the flow-proportional sampling the permit requires, it is reported daily to the regulator, and it is the basis for the plant capacity rating. It is measured in an open channel with a Parshall flume and a level sensor, or in a pipe with a magnetic flowmeter where the influent is pumped, and either way it gets the best installation and the most frequent verification of any instrument on site. The open channel flow page covers the flume; the mag meter page covers the pipe. A second flow measurement, at the plant effluent or at the influent pump station, gives a cross-check that catches a fouled flume sensor before the monthly report does.

Screens

Mechanical bar screens and fine screens remove material that would damage pumps and clog diffusers. A screen accumulates debris on its face, the water level upstream rises as the screen blinds, and the screen rake or brush cleans the face on a cycle. The control decides when to cycle.

Differential level
Level sensors upstream and downstream of the screen; the difference is the head loss through the accumulated debris. A cleaning cycle starts when the differential exceeds a setpoint, commonly a few inches, and runs until the differential drops or a set number of rake passes completes. The primary control.
Timer
A cycle on a fixed interval regardless of differential, so a screen with a failed level sensor still cleans, and so debris does not sit on the face during low flow and go septic.
Continuous during high flow
Above a flow or an upstream level setpoint, the screen runs continuously; a storm brings the debris of the whole collection system at once.
High differential alarm
A differential that keeps rising with the screen running means the screen cannot keep up, is jammed, or has failed. The alarm is high priority because the next event is the channel overflowing the screen or the bypass opening.
Bypass
A bypass channel with a coarse bar rack, opened manually or by a gate that lifts on high upstream level, so a failed screen does not back up the collection system. The bypass event is logged and, in most permits, reported.

The screen drive has its own protection: a torque or current limit that stops the rake on a jam, an overload, and often a reverse-and-retry routine before it alarms. Screenings drop into a washer compactor or a conveyor that runs when the screen runs plus a lag time, and the compactor has its own jam detection.

Grit removal

Grit, the sand and small dense solids that pass the screen, settles in a grit chamber, a vortex unit, or an aerated grit tank, and is pumped out to a classifier that separates it from the organics and dewaters it. The grit pump runs on a schedule, every hour for a few minutes, or on the flow, longer and more often at high flow when the grit load is higher. The classifier runs with the pump plus a lag. An aerated grit tank has an airflow setpoint that sets the roll velocity, high enough to keep organics in suspension and low enough to let grit settle, and it is adjusted with flow.

Influent pumping

Plants below the collection system grade have an influent pump station at or before the headworks, and it is a lift station with the largest pumps in the utility, controlled as the lift station pages describe, with a wet well level loop, staging, and a backup path. Two headworks-specific points: the pumps are usually after the coarse screen so they are protected from the worst debris, and the station capacity and its high level alarm define the plant peak hydraulic capacity and the point at which a bypass or a storage basin comes into use.

Storm response

The headworks sees a storm before the rest of the plant. A rate-of-rise on the influent flow, a rising channel level, and the collection system lift stations calling their lag pumps all arrive together, and the headworks controls respond: screens to continuous cleaning, grit pumps to their high-flow schedule, influent pumps staged up, and the plant flow split logic that decides when flow above the treatment capacity goes to equalization or to a wet weather treatment path. The setpoints for those transitions are in the control narrative and are the most consequential numbers in the headworks program.

What SCADA needs

  • Influent flow, totalized daily, with the meter verification record.
  • Screen differential level, cycle count, run time, and jam events.
  • Grit pump and classifier run status and cycle counts.
  • Influent pump station status as for any lift station.
  • Gas detector readings and ventilation status, alarmed at high priority.
  • Bypass gate position and bypass events, logged for reporting.
  • Channel and wet well levels, with high alarms.
  • Equipment availability: every device in the headworks with its HOA and fault.

Frequently asked questions

Why does the screen cycle constantly at night?
The differential setpoint is too close to the head loss of a clean screen at low flow, the downstream level sensor is reading low, or debris is hanging on the face and never clearing. Check the two level sensors against a tape, raise the differential setpoint a little, and inspect the screen face and the rake.
How is the influent flume checked?
The head measurement is compared with a staff gauge at the measuring point on a schedule, and the flume dimensions are checked against the standard when there is any doubt. An independent flow measurement, such as a mag meter on the influent pump discharge or the effluent flow adjusted for plant use, gives a daily cross-check.
What runs the grit pump when the flow meter fails?
The schedule. Grit pumping on a fixed interval is the fallback for the flow-paced mode, and the program falls back automatically when the flow signal is invalid, with an alarm. The classifier follows the pump.
Can the headworks panels be inside the building?
Only if the room is unclassified or the panels are rated for the classification. The usual design puts the panels in an electrical room outside the classified boundary with intrinsically safe barriers or rated wiring methods for the instruments inside it. NFPA 820 and the electrical engineer set the boundary.

Direct contact