Produce the terminal schedule that lets a technician find any wire: define the strips and their numbering, list every terminal with its wire numbers, the device and the field destination, and keep it current through every change.

7 min readUpdated Sep 5, 2026Published Sep 5, 2026By Eric Sullivan

The short answer

How to Build Terminal Schedules

To build a terminal schedule, define the terminal strips of the panel by voltage class and function with a designation and a numbering scheme, then list every terminal on every strip with the wire number on the panel side, the wire or cable and conductor on the field side, the device each connects to, and the field destination with its drawing reference; generate the list from the schematic with the drafting tool or a spreadsheet driven by the wire numbers, so that the schedule and the drawing cannot disagree; mark the spares; check it against the built panel terminal by terminal and against the field cables at pull-in; and put it in the panel pocket and the engineering library with a revision, updating it as part of every change rather than afterward.

Key points

  • Strips by voltage class and function, each with a designation and a numbering scheme fixed for the plant.
  • Every terminal: panel wire number, field cable and conductor, device, destination, drawing reference.
  • Generate from the schematic; a schedule typed by hand diverges from the drawing on the first change.
  • Reconcile at panel checkout and at cable pull-in; mark spares explicitly.
  • Revision controlled, in the panel pocket and the library, updated with every change.

What you need

  • The panel schematic with wire numbers and terminal designations
  • The cable schedule and the I/O list
  • The drafting tool report function, or a spreadsheet template with the schedule columns
  • The plant numbering convention for strips, terminals, and wires
  • Terminal markers and a label printer for the panel

Procedure

  1. 1

    Define the strips

    One per voltage class and function: power distribution, 120 volt control, 24 volt discrete inputs, 24 volt discrete outputs, analog, network, intrinsically safe, and grounds. Designate each, for example TB1 to TB8 or by function, per the plant convention.

  2. 2

    Set the numbering

    Terminals numbered sequentially within each strip; multi-level terminals with a level suffix; wire numbers by the plant convention, such as sheet and line, so that a wire number locates the schematic.

  3. 3

    Assign the field connections

    From the I/O list and the cable schedule: each field point lands on a pair or a group of terminals on the strip for its class, grouped by cable so that a cable lands on adjacent terminals, with shield terminals beside the analog pairs.

  4. 4

    Draw it

    On the schematic, every field connection shows the strip and terminal; the wire numbers on both sides. The drawing is the source.

  5. 5

    Generate the schedule

    The drafting tool report or a spreadsheet built from the wire list: strip, terminal, panel wire number, panel device and terminal, field cable and conductor, field device, destination drawing. Sort by strip and terminal.

  6. 6

    Mark spares

    Every unused terminal listed as SPARE; spare cable conductors listed against their cable and marked spare at both ends.

  7. 7

    Check the panel

    At panel checkout, walk every strip with the schedule: the marker, the wire number, and the destination match; corrections go back to the schematic first, then the schedule is regenerated.

  8. 8

    Check the field

    At cable pull-in and termination, each conductor landed per the schedule, and the schedule corrected for any field change with the reason.

  9. 9

    Issue it

    A revision number and date; a copy in the panel pocket, one in the engineering library with the schematic, and one with the commissioning records.

  10. 10

    Maintain it

    Every change to the panel starts with the schematic and ends with a regenerated schedule and a new pocket copy. A schedule that is not updated is a trap.

ColumnContentExample
StripTerminal strip designationTB3 (24 VDC inputs)
TerminalNumber and level14, 14L (lower level)
Panel wireWire number on the panel side1234
Panel deviceDevice and terminal it connects toDI-1 slot 2 ch 6
Field cableCable number and conductorC-120 / 3 (black)
Field deviceTagLSH-101
DestinationLocation and drawingWet well JB-1, sheet E-12
NotesShield, spare, fused, disconnectShield to SH bar

Frequently asked questions

Spreadsheet or drafting tool report?
The drafting tool report where the schematic is drawn in a tool that tracks wires; it cannot disagree with the drawing. A spreadsheet driven from the wire list otherwise, with a discipline that the drawing changes first.
How do I number terminals on a multi-level block?
One number per position with a level suffix, upper, middle, lower, or U, M, L, and the schematic drawn to show the levels. A three-level strip drawn as flat terminals is where wiring errors come from.
What about junction boxes in the field?
Each junction box has its own schedule on the same pattern, with its cable in and cables out, and the panel schedule references the box and its terminal. The chain from panel to device is traceable through the schedules.
The panel shop wired it differently from the schedule.
Find out why; sometimes the layout forced it. Then the schematic is corrected to what was built, the schedule regenerated, and the panel re-marked if needed. Never two documents that disagree.

Direct contact

Have a controls question?

Reach Eric Sullivan directly about anything on this site, a controls or automation topic, or one of his personal projects.